Different Rates by Name
Great App. It would be great if you could define different rates for departments instead of putting in $ values. For example: Define the hourly rate for engineering as 90$ . When I add an engineering task I could just choose " Engineering" and the hourly rate would be adjusted to 90$.
Thanks Chris
Thank you for the idea.
WBS supports to change the charge rate (“by input”) of a WORK GROUP, after changed the rate of a group, the sub-work’s charge rate will change to the same. Would you please help to check if you can use this approach.
WBS is used at the very early phase of a project (normally before project kick-off), at that time, normally the project team is not ready, and the charge rate is rough (or available) for estimate purpose.
If you are working on project schedule (for planning and also for the accurate cost calculate), I’d suggest you to try the project schedule app QuickPlan.
Best Regards,
Philip