NORMALLY!, the process of a project is: … → Breakdown Work (estimation) → SOW (contract) → High level plan → Schedule → executing and report → …
- WBS is for work breaking down, the project team will use it to evaluate the estimate, time and resources needs for contract.
- WBS is NOT to assign resource and plan the efforts
- WBS work is NOT same as project task ( there are many methods to break down work, for example by delivery, a delivery will NOT be same as a task)
- WBS can be a good reference for later planning, but the work in the WBS is not the list of the tasks when planning
That means WBS is not the step to maintain the schedule (the relationship of task, time and resource)but NATURALLY,
- people like the way WBS do to report project status…Anonymous supported this idea · -