An error occurred while saving the comment An error occurred while saving the comment Anonymous commentedAt least adding project status will be really helpful and we can use this for status reporting on large project
Anonymous supported this idea · -
6 votesAdminPhilip Lee (Supporter, Mobilinked) responded
NORMALLY!, the process of a project is: … → Breakdown Work (estimation) → SOW (contract) → High level plan → Schedule → executing and report → …
- WBS is for work breaking down, the project team will use it to evaluate the estimate, time and resources needs for contract.
- WBS is NOT to assign resource and plan the efforts
- WBS work is NOT same as project task ( there are many methods to break down work, for example by delivery, a delivery will NOT be same as a task)
- WBS can be a good reference for later planning, but the work in the WBS is not the list of the tasks when planning
That means WBS is not the step to maintain the schedule (the relationship of task, time and resource)but NATURALLY,
- people like the way WBS do to report project status…Anonymous supported this idea · -
5 votesAnonymous supported this idea ·
-
6 votesAnonymous supported this idea ·
Target data is already there which is really useful. Adding percent complete will be really really awesome feature.