I’m referring to this old thread not to open too many new threads.
In WBS you provide a target date. When sending the WBS file to QuickPlan I see all my work packages with the appropriate target date and a duration of 1 day.
If I add the duration >1 to my work packages the target date jumps to the future. I would have expected that the start date jumps backwards, target date minus duration and the target date remains as set in WBS.
I’m referring to this old thread not to open too many new threads.
In WBS you provide a target date. When sending the WBS file to QuickPlan I see all my work packages with the appropriate target date and a duration of 1 day.
If I add the duration >1 to my work packages the target date jumps to the future. I would have expected that the start date jumps backwards, target date minus duration and the target date remains as set in WBS.
Regards
Uli